How does a Europea built-in pool is installed

How does a Europea built-in pool is installed

Installation steps
• Survey land and determine pool height as per customer’s expectations and ground topography: 30 minutes.
• Excavation: 3 to 5 hours 
• Pool positioning as per agreement with the customer and location plan: 30 minutes
• Panel installation: 3 hours
• Lights and water inlet installation: 1 hour
• Linen holding device installation: 30 minutes
• Steps installation: 30 minutes
• Filtration base installation: 15 minutes
• Checking pool level: 15 minutes
• Wall alignment: 15 minutes
• Perimeter plumbing installation: 1 hour
• White part preparation: 30 minutes
• Pump installation: 30 minutes
• Concrete casting: 1.5 hours
• Stone packing: 2 hours
• Concrete levelling: 1 hour
• Decorative stone installation: 4 hours
• Drop installation: 2 hours
• Capping installation: 2 hours
• Linen installation: 2 hours
• Filtration equipment installation: 2 hours
• Pool filling: variable

Related posts

Help Center